Tuesday 24 April 2018 – Handover

Handover Inspection - 23 April We had our Handover Inspection with our SS yesterday.  We went through the PCI Report from Darbecca and also Bentley's list and checked everything off.  A few things were outstanding; the mullion on the stacker screen door, and the hole in the flyscreen on the stacker.  These are ordered through…

Advertisements

Monday 20 November 2017 – Belated Construction Update

We received our construction update on Friday last week and was told that cabinetry is complete and fixing is due to start this week.  We were originally told that fixing was due to start 2 weeks ago, but we haven't been given an explanation for the delay.   In response to our questions/concerns/issues, we were…

Friday 13 October 2017 – Defect Update

This week has been a roller coaster of emotions and a lot of back and forth of emails between us and the builder.  I have calmed down, mostly.   So the reinspection report.  There were still a few items affecting the frame that hadn't been done.  They were the sticking points for us as once…

Tuesday 10 October 2017 – Fail

No.  Not everything has been fixed.  And our SS didn't turn up for the re-inspection, he did say that he would be there, and that's why Mr W took the morning off work, so that he, the SS and the Inspector could get together and cross things off.   I'm beyond disappointed.   I''m not…